05/12/16 – The good old heave-ho. 

Today we had originally been planned in to run a supply cable from a distribution board to a newly installed compressor . 

The original plan was to run the cables though the cable channel that was already installed, however when we came to use the channel we found that the old cable that needed replacing was stuck in the channel and couldn’t be moved . 

After trying a whole variety of different ways to install the cable but nothing was working, we eventually had to cancel the job so that we could order relevant parts so that the cable can be mounted along the wall instead. 

Dan 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s