02/11/16 – one , two , three lift !!

I spent the morning at a sewage treatment works over in the weatherby area as we needed to remove the central inlet and outlet pipes from a grit removal system. 

Although it appeared to be a easy job it required the use of a hiab crane and a very long sledge hammer to help remove the equipment as it had seized into place and the grit needed to be removed so that the pipes could be lifted out . 